The Crowlands Wind Farm consisted of 39 Senvion MM92 wind turbine generators, situated in western Victoria. ARES transported all wind turbine components from the Port of Portland to site, a distance of 250km one way.

Key Statistics

39
Senvion WIND TURBINES

Each MM92 turbine stands almost 150m tall (base to tip), and produces 2.05MW of green power.

36m
Longest tower section

The top tower section was the longest we have ever transported, requiring special bookend trailers.

250
KM’s TO SITE

The journey took around 5-6 hours, including slowdowns and fatigue breaks.

316
TOTAL DELIVERIES

These include turbine components, towers, blades, transformers and containers.

Project Challenges

The terrain was the defining problem: winding, undulating hills with gradients of up to 20% that needed a tow train to beat, plus loads up to 57m long threaded around the towns of Hamilton and Ararat, and shared port storage to keep in order.

Steep, winding terrain

The terrain at Crowlands was especially tricky, with winding and undulating hills and road gradients of up to 20%. To get the larger loads up, Ares brought in the heavy duty BIGFOOT tow truck, and for the steepest sections added a Moxy dump truck to form a three-truck tow train that could navigate to the top.

The top tower section was the longest Ares had ever transported, needing special bookend trailers. The 36m mid tower sections were another standout: on the bookend trailers the truck and trailer combination reached 57m, even longer than the blade trailers, so special care was needed around the large towns of Hamilton and Ararat to avoid damage to cargo and road infrastructure.

Crowlands and Murra Warra were both delivered out of the Port of Portland and had to share storage space, around 100 turbines’ worth of components between them. Everything had to be segregated by type and project, some stored berthside and the rest sent to the nearby storage area in Portland.

Results

Ares delivered the turbine components for the Senvion MM92 turbines from the Port of Portland to the Crowlands site, managing shared port storage with the neighbouring Murra Warra project and threading loads up to 57m long around Hamilton and Ararat without damage to cargo or road infrastructure.

The steepest, most awkward loads were hauled up gradients of as much as 20 percent, using the BIGFOOT tow truck and, where it wasn’t enough, a three-truck tow train built with a Moxy dump truck to reach the top. It was part of a three-project portfolio awarded by Senvion in 2018, alongside Murra Warra Stage 1 and Lincoln Gap Stage 1.