Level Crossing Removal Project 2 2023

Featured Project

125-Ton L-Beams Through the Metropolitan Maze

Project Scope:
Route Planning
Delivery
Night Transport

Ares transported precast concrete L-beams, each weighing 125 tons and up to 30m long and made by CIG in Laverton, to level crossing removal sites at Webb St in Narre Warren and at Waurn Ponds. For Narre Warren the beams took the Metropolitan Ring Road around Melbourne to Greensborough, then wound through the eastern suburbs onto the M3, Eastlink and M1 down to site, while the Waurn Ponds loads ran the M1 past Geelong.

Key Statistics

80
L-BEAMS TRANSPORTED

L-beams delivered across both sites

30m
Component LENGTH

The L-Beams had to be made as long as possible to reduce the number of spans required for each crossing.

130t
BEAM WEIGHT

The beams are made of pre-cast concrete with steel reinforcing bars embedded throughout.

0
Incident or accident

Especially impressive given the size of the beams and the restricted space we had to manoeuvre on site.

Project Challenges

The U-troughs were so heavy they had to be split into 125-ton L-beams just to move, and even split they combined extreme weight with lengths of up to 30m, which Ares carried on three trailers each through the tight metropolitan areas of Melbourne and Geelong, including a Waurn Ponds crossing with only a four-night closure window.

Too heavy to move whole

Level crossing removals use an elevated rail overpass built from precast U-troughs, strong enough to carry the fill material, rail tracks and the trains themselves. That makes them very heavy, so they had to be split in half into L-beams just for transport, and each half still weighed 125 tons.

To minimise the number of spans in the overpass, the beams were also very long, up to 30m. To handle that combination of weight and length, Ares used three trailers per L-beam, a dolly, low loader and jinker, keeping axle loads acceptable while staying manoeuvrable enough for the metropolitan areas around Melbourne and Geelong.

From CIG in Laverton, the Narre Warren beams took the Metropolitan Ring Road around Melbourne to Greensborough, wound through the eastern suburbs, then ran the M3, Eastlink and M1 down to site. The Waurn Ponds loads took the M1 all the way past Geelong before exiting to reach the construction site.

The Port Kembla run was straightforward but for a few tricky corners through Goulburn before the two site entrances.

Results

On the largest of the Level Crossing Removal Project’s awarded sub-projects, Ares delivered some 400 Super Tee beams from Melton to level crossings across Melbourne’s south-east, from Murrumbeena to Noble Park, at 4 to 6 a night and over the West Gate Bridge and through the Burnley Tunnel under permit.

 

With the work built around active rail lines and over half the deliveries time-sensitive, every segment arrived on time and without any disruption to Metro Trains, delivered to the Tier 1 safety standards the project demanded.