Biala Wind Farm

Featured Project

Turbine transport with a purpose-built trailer

Project Scope:
Route Survey
Planning & Permit
Delivery
Storage & Offload

The Biala Wind Farm consisted of 31 Goldwind GW136 3.5MW wind turbine generators,
situated near Goulburn in New South Wales. ARES transported all wind turbine components from
the Port of Port Kembla to site, a distance of 220km one way.

Key Statistics

31
Goldwind Wind Turbines

Each turbine stands 180m tall (base to tip), has 6 tower sections and produces 3.5MW of green power.

16 weeks
Transport Duration

Components were on the road between February and August 2020.

220
KM’s TO SITE

The journey took around 5-6 hours, including slowdowns and fatigue breaks.

427
Total Deliveries

These include turbine components, towers, blades, transformers and containers.

Project Challenges

The nearest port, Port Kembla, sat behind a 5.3m low bridge that no existing trailer could clear while carrying the 4.8m diameter, 110-ton tower base sections. Ares designed a modified trailer to fit, then delivered all 31 turbines through the town of Crookwell in 16 weeks.

The low bridge

The logical port of import was the nearest one, Port Kembla, but with base tower sections at 4.8m in diameter and 110 tons in weight, there was no existing trailer combination that could both safely carry the tower and pass under a 5.3m low bridge in Wollongong. The alternate port of Newcastle was nearly double the distance away, and would have been a much costlier and riskier solution as a result.

When Goldwind Australia approached Ares with the problem, our solution was simple. If no trailer exists, then we shall design one to suit. The result was a modified platform trailer, strong enough to hold the weight of the massive tower, but with a cut-out to allow the tower to sit lower than normal. At a loaded height of 5.1m it could clear the low bridge and allowed Goldwind to use their preferred port, resulting in substantial savings for the project.

Unlike the Crookwell 2 route two years prior, Biala meant traversing the town of Crookwell itself with longer blades. Several corners in Crookwell had to be specially modified to accommodate the 69m-long blades before the short final run to site.

All Biala deliveries were executed and completed within 16 weeks, an average of almost two complete wind turbines per week. That run rate held despite ship discharges, the Easter long weekend and disruption due to COVID-19, and came down to the combined efficiency of the AAT port loading crews, the Ares team, the customer’s offloading crews on site, and clear communication and coordination between all parties.

Results

Ares delivered all 31 turbines’ components from Port Kembla within 16 weeks, at almost two complete turbines per week, despite ship discharges, the Easter long weekend and COVID-19. The custom trailer let Goldwind keep their preferred port and brought substantial savings.

 

Goldwind described the work as a comprehensive solution covering planning, permitting, vessel discharge and delivery to site, run day to day by highly skilled professionals, and credited the flexibility and efficiency shown across the project with helping achieve the target under budget.

Trusted by Our Clients

We are very pleased with ARES and the logistics service they have provided at Biala Wind Farm for WTG transport.  Their comprehensive solution covers every key aspect including planning, permitting, vessel discharge, and delivery to site, and the daily operation is well managed by highly skilled professionals.  Their performance has been recognised by not only the project team but also our subcontractors.  The flexibility and efficiency they have demonstrated throughout the Biala project helped us achieve the target under budget.  I trust they will continue with excellent performance on future projects and wish for the next opportunity to work with them again.

Andy Wang - TSI Project Manager

Goldwind Australia

Discuss how our solutions
can benefit your project.

DISCUSS YOUR PROJECT WITH US
Scroll to Top